Maseve Data

Maseve Information

  • Geology 2015-09-05
    The Bushveld Complex is an enormous body of rock that cooled from a molten intrusion 2 billion years ago. The intrusion is more than 330 kilometers across at surface and can be seen from space. In geological terms, molten intrusive bodies in the earth are not uncommon, but the massive Bushveld Complex, so far in the known world, is a unique occurrence. This large intrusion is thought to have tapped deep into the earth and cooled and mixed in such a way that platinum and palladium mineralization was concentrated and settled into distinct and continuous layers, each approximately 1 metre thick. The exact mechanisms that formed these bowl-like platinum and palladium bearing layers are still hotly debated, but the extraordinary continuity and grade of these layers across enormous distances is well demonstrated. The Merensky and UG2 (Upper Group layer #2) Reefs are the main layers mined for platinum in the approximately 20 mines around the perimeter of the Bushveld Complex. There is extraordinary continuity and predictability of the platinum-bearing layers of the Bushveld Complex and rarity in the Bushveld Complex setting.
  • General 2015-05-10
    The Western Bushveld Joint Venture is a unique platinum project likely to be one of the last large-scale near-surface developments on the high-grade Merensky and UG2 platinum reefs of the Western Limb of the Bushveld Complex. The WBJV Project 1 has advanced to construction. We are currently focused on developing our underground access decline tunnels and executing on the second phase of construction. The WBJV Project 1 Platinum Mine is owned 74% by Platinum Group Metals Ltd. and 26% by Wesizwe Platinum Limited (WEZ-JSE). Wesizwe is owned 45% by Jinchuan Group, a state owned company from China. Wesizwe is building the adjoining Bakubung Platinum Mine, a deeper mine with a cost recently estimated at USD$1.5 billion.

Related News

  • PTM to advance Waterberg PGM project to feasibility, construction decision stage 2016-10-20
    Having received positive results from an independent prefeasibility study (PFS) on the Waterberg platinum group metals (PGM) project, in Limpopo, TSX- and NYSE-listed Platinum Group Metals (PTM) plans to advance the project to the completion of a feasibility study (FS) and a construction decision. Under the PFS model, first production at the PGM project is estimated to be in mid-2021, if the FS is completed at the end of 2017 and a mining right and other permits are granted as planned.
  • Wesizwe concludes early termination of Bakubung contract with Aveng 2016-09-30
    Emerging miner Wesizwe Platinum concluded an amicable agreement with appointed shaft sinking contractor Aveng Mining for an early termination at its Bakubung platinum mine, in Rustenburg. The agreed handover will be concluded by May 2017, when Phase 1 main shaft commissioning, which was initially to be concluded by September, will be completed.
  • Despite reaching production vein, PTM lowers guidance again as stoping delays weigh 2016-09-19
    South Africa-focused miner Platinum Group Metals (PTM) has again lowered its production guidance for the first year of operations at its Maseve mine, in South Africa, citing a delay in ramping up stoping tonnes. Despite monthly output at Maseve increasing to 1 893 oz of platinum, palladium, rhodium and gold (4E) and associated copper and nickel in concentrate, the Vancouver-based company advised that it has amended lower its guidance for concentrate production, on a 100% project basis from April 2016 to April 2017, from 110 000 oz 4E to 91 500 oz 4E.
  • Despite reaching production vein, PTM lowers guidance again as stoping delays weigh 2016-09-19
    South Africa-focused miner Platinum Group Metals (PTM) has again lowered its production guidance for the first year of operations at its Maseve mine, in South Africa, citing a delay in ramping up stoping tonnes. Despite monthly output at Maseve increasing to 1 893 oz of platinum, palladium, rhodium and gold (4E) and associated copper and nickel in concentrate, the Vancouver-based company advised that it has amended lower its guidance for concentrate production, on a 100% project basis from April 2016 to April 2017, from 110 000 oz 4E to 91 500 oz 4E.
  • Waterberg, South Africa: 5.5m grading 9.05 g/t 3E (2.16 g/t Pt, 5.32 g/t Pd, 1.57 g/t Au) from 1006.5 meters (WB208) 2016-05-31

Maseve News

  • Despite reaching production vein, PTM lowers guidance again as stoping delays weigh 2016-09-19
    South Africa-focused miner Platinum Group Metals (PTM) has again lowered its production guidance for the first year of operations at its Maseve mine, in South Africa, citing a delay in ramping up stoping tonnes. Despite monthly output at Maseve increasing to 1 893 oz of platinum, palladium, rhodium and gold (4E) and associated copper and nickel in concentrate, the Vancouver-based company advised that it has amended lower its guidance for concentrate production, on a 100% project basis from April 2016 to April 2017, from 110 000 oz 4E to 91 500 oz 4E.
  • PTM completes Maseve plant commissioning, lowers guidance 2016-05-05
    On the heels of completing commissioning of its Maseve mine plant on March 31, South Africa-focused precious-metals producer Platinum Group Metals (PTM) has produced about 1 700 ‘4E ounces’ containing platinum, palladium, rhodium and gold in April alone. The Vancouver-incorporated company advised Thursday that during February, March and April, a majority of milled tonnes were sourced from lower-grade development muck mined from primary development along the rich Merensky Reef of the country’s fabled Bushveld Igneous Complex.
  • Platinum Group Metals Reports Completed Hot Commissioning Test for the Maseve (WBJV Project 1) Platinum Mine 2016-02-09

    VANCOUVER, BRITISH COLUMBIA and JOHANNESBURG, SOUTH AFRICA--(Marketwired - Feb. 9, 2016) - Platinum Group Metals Ltd. (TSX:PTM)(NYSE MKT:PLG) ("Platinum Group" or the "Company") reports the Maseve (formerly WBJV Project 1) Platinum Mine has successfully completed its 72 hour run test during Hot Commissioning of its concentrator facility. The mine has produced its first concentrate for delivery to the Anglo Platinum Waterval smelter 40 kms to the south of the mine.

  • PTM targets first concentrate production at Project 1 mine in January 2016-01-15
    Dual-listed Platinum Group Metals (PTM) expects the first concentrate production at its Western Bushveld Joint Venture Project 1 platinum mine to start late in January, with first concentrate deliveries to Anglo American Platinum scheduled for February. Hot commissioning of the Project 1 plant was under way, while underground development was ongoing.
  • PTM to start WBJV Project 1 hot commissioning after closing $80m financing 2015-11-20
    Project developer Platinum Group Metals (PTM) will start with hot commissioning of the Waterberg Joint Venture (WBJV) Project 1 plant, located near Rustenburg, South Africa, after closing and drawing down $80-million in separate financings on Friday. "We are very pleased to complete this transaction with the clear support and vision of our major shareholders. We look forward to the ramp up of our first mine with an eye on continued solid demand for platinum and palladium and improved markets in the near and medium term,” PTM co-founder and CEO Michael Jones stated.

Nearby Locations

Nearby Location News

  • Wesizwe concludes early termination of Bakubung contract with Aveng 2016-09-30
    Emerging miner Wesizwe Platinum concluded an amicable agreement with appointed shaft sinking contractor Aveng Mining for an early termination at its Bakubung platinum mine, in Rustenburg. The agreed handover will be concluded by May 2017, when Phase 1 main shaft commissioning, which was initially to be concluded by September, will be completed.
  • Wesizwe’s flagship Bakubung mine still on target 2016-03-30
    Platinum miner Wesizwe Platinum remains within its targeted concentrate production output and project construction costs budget for its flagship Bakubung project, in Rustenburg. Reporting on its 2015 financial year performance, the Chinese-backed company said that, during the year to December, the main and ventilation shafts were completed as scheduled at 825 m and 810 m respectively. Further, services projects on site were on schedule, with an additional 20 MWa secured for the phase one power supply for the commissioning of the shafts and 1.5-million-litres-a-day capacity had been commissioned for permanent water supply to the mine.
  • RBPlat posts FY loss, delays projects 2016-03-01
    Ongoing depressed market conditions and a low commodity price environment have prompted South African platinum miner Royal Bafokeng Platinum (RBPlat) to delay some of its capital projects. During the second half of the 2015 financial year, RBPlat had scaled down mining and construction activities at its Styldrift I expansion project, deferred the 250 000 t/m Bafokeng Rasimone Platinum Mine (BRPM) concentrator upgrade to early 2016, deferred the construction of a 100 000 t/m concentrator module and deferred the Styldrift II feasibility study and exploration drilling, besides other initiatives to reduce noncritical expenditure.
  • Wesizwe marks another Bakubung milestone, prepares for shaft commissioning 2015-12-09
    The completion of the latest shaft sinking milestone at platinum hopeful Wesizwe Platinum’s Bakubung platinum mine, near Rustenburg, has marked the start of shaft equipping and commissioning. Work at the Chinese-backed flagship mine continued to develop at pace as Wesizwe’s shaft sinking programme culminated with the last vertical blasts pushing the main shaft down to a depth of 826 m at 82 level and the ventilation shaft reaching a depth of 816 m at 81 level.

Top Mining News

  • Ecuador approves EIS for Lundin Gold’s Fruta del Norte project

  • Atalaya’s quarterly copper production doubled as Proyecto Riotinto ramp up continues

  • Aucu delivers more high grade results

  • Trevali expands high-grade Santander deposits, makes new hanging-wall discovery

  • Nordgold launches Bouly operation in Burkina Faso