  • General 2015-05-10
    With a view to improve the existing level of production and productivity, company has started work of sinking of vertical shaft upto 156 Meters depth of 4.5 mtrs dia. Vertical shaft sinking work started in May - 2010 and scheduled completion period is 48 months. Sinking upto depth of 82 Meters has already been achieved against the total sinking of 156 Meters. The project is expected to increase production from 50000 TPA to 100000 TPA and also life of mine.